Enabling Infrastructure Design Total – Tilenga

The Tilenga project was divided into two main packages namely; The upstream facilities which are subject to separate feed contracts and enabling infrastructure.

Our enabling infrastructure services contract included the design of early works to enable upstream facilities works which include the below; –

  • 30 well pads (reduced from 35) and the upstream gathering network
  • The Central Processing Facility (CPF)
  • Nile River Crossings with block valve stations
  • Water Abstraction Pipeline from Lake Albert to the Central Processing Facility (CPF)
  • Construction Camp and Support Base, Operation Camp and Support Base